3.2 Basic Operation Procedure
35
3.2 Basic Operation Procedure
The following steps should be formed before other operation procedure to take
measurements.
3.2.1 Step 1. Getting Started
1. Make sure the connections have been made between HOST and HOST Controller on
the rear panel of the TC-3000C via RS-232C or USB.
2. Connect the RF port of theTC-3000C to the DUT using RF cable or the 2.4GHz
antenna.
To maintain regulatory compliance, OTA (over to air) connection to the DUT
must be carried out within an adequately RF isolated environment with reliable
RF coupling.
3. If DUT has the HCI port, connect the DUT to the USB ports on the front panel of the
TC-3000C.
4. Set DUT to the Inquiry/Page scanning mode with test mode enabled. If the DUT is
connected to the TC-3000C by using a standard USB(HCI), you don’t need to do this
step because the TC-3000C can control the DUT automatically.
Before running a test the DUT must be initialized so that it is Inquiry/Page
scanning. If test mode is not enabled, the TC-3000C will use null packet mode
for measurement and test.
5. Press the soft switch (Item #16 in the figure on page 24) on the front panel. After the
system booting process, the TC-3000C display the Start-up screen that is going to be
changed to initial test screen 10 seconds later.
6. Make sure the “HCI Port” of DUT configuration: Press Menu Select
“Configuration” from the pop-up menu on the screen M2 (DUT) F3 (HCI
port). Make sure the “HCI Port” of DUT configuration is correct for the HCI port of the
TC- 3000C in use. If the DUT is not connected to the HCI port of the TC-3000C, “None”
must be selected.