12.6 Master and Slave Synchronized Measurement
Procedure
Making the WT500 the Master or the Slave
1.
Press SETUP to display the Setup menu.
If the full Setup menu does not appear, proceed to step 2. If the full Setup menu appears,
proceed to step 4.
2.
Use the cursor keys to select Details.
3.
Press SET to display the full Setup menu.
4.
Use the cursor keys to select Measure.
5.
Press SET to display the Measure Settings dialog box.
6.
Use the cursor keys to select Sync Measure.
7.
Press SET to select Master or Slave.
You can only set one instrument as the master and one instrument as the slave.
Performing Synchronized Measurement
Connect the external start signal input/output connectors (EXT CLK) of the master and
slave instruments using a BNC cable (sold separately).
The slave instrument starts measuring at approximately the same time as the master
instrument.
The slave instrument stops measuring at approximately the same time as the master
instrument.