Explanation
The measurement period is determined by the data update rate (see section 4.9 for 
details) and by the synchronization source, which is specified by following the procedure 
described in this section. For details, see appendix 6.
During normal measurement, numeric data is measured or computed from the data 
sampled within the measurement period.
Setting the Synchronization Source
Only installed elements appear. For each element, you can select which input signal will 
be the synchronization source (the measurement period will be synchronized to the zero-
crossing point of the input signal). You can select the synchronization source signal from 
the choices listed below. The selectable items vary depending on the installed elements. 
When independent element configuration is off, the synchronization source for all 
elements in a wiring unit is determined by the synchronization source of the first element 
in the wiring unit.
  U1, I1, U2, I2, U3, I3, Ext Clk (external clock), and None
Note
If you specify no synchronization source by selecting “None,” all of the sampled data within the 
data update interval is used to determine the numeric data. When measuring DC signals, this 
method can be used to prevent errors in the detection of the measurement period caused by 
noise.
When Setting the Synchronization Source to Ext Clk
Apply a clock signal that meets the following specifications to the external clock input 
connector (EXT CLK) on the rear panel.
   
•  Ext Clk Specifications
Item Specification
Connector type BNC connector
Input level TTL
Input waveform 50% duty ratio rectangular wave
  CAUTION
Applying a voltage outside of the range of 0 to 5 V to the external clock input 
connector (EXT CLK) can damage the WT500.
Note
•  The synchronized measurement slave setting and the synchronization source Ext Clk 
setting cannot be made at the same time because they both use the same connector (see 
section 12.6 for information about synchronized measurement).
•  To connect a BNC cable to the external clock input/external start signal output connector 
(EXT CLK) when a GP-IB cable is connected to the GP-IB connector, first remove the GP-IB 
cable. Then connect the BNC cable. Finally, reconnect the GP-IB cable.