8. From the openings (1), route the cables to the terminals (2) as illustrated in
the examples for ARU / INU / IFU 9 MVA and LSU.
Figure 5-12 ARU/INU/IFU cable routing
Figure 5-13 LSU cable routing
9. Connect each wire to terminal block -X1 according to the terminal numbers
printed on the marker sleeves (white).
10. In the upper part of the cable duct (1), fasten the cables to the cabinet frame.
11. In the lower part (2), tie the cables together at regular distances.
12. Check that the cables do not touch the DC busbars.
1 1
2
1
2
15 x
1 1
2

Table of Contents