6.8.8.2. Routing cables through the REB (WCU)
1. If present, remove the blanking plate.
The plate can either be discarded or used as an entry plate.
2. Route the cable along the WCU side wall, through the cable transit and to the
receiver.
3. To fix the cables to the rails on the side wall, use a screw base with a cable tie
or cable clamps appropriate for fiber optics.
4. To seal the cable entry, use appropriate sealing inserts for the cable entry
frames.
Figure 6-43 REB cable entry
1) Blanking plate (removed)