COMMISSIONING
PRODUCT
ACS6000
DOCUMENT KIND
User manual
DOCUMENT ID.
3BHS212794 E01
REV.
N
LANG.
en
PAGE
158/266
7.6. Commissioning checklists
The following checklists are designed to help you prepare the drive and associated 
equipment for commissioning.
7.6.1. Mechanical installation checklist
1) Drive is aligned according to drive layout drawing (if delivered in several 
transport units) and installed according to the instructions in this user 
manual (3BHS212794 E01 N).
□
2) Drive is securely fixed to the floor.
□
3) Roof attachments are installed (if applicable).
□
4) Pipe joints are orientated and torqued correctly.
□
5) Joints for DC link and ground busbar are installed and correctly torqued.
□
6) Roof-mounted fan units are installed (if applicable).
□
7) Raw water piping is completed and pipes are flanged to the drive (if 
applicable).
□
8) Raw water supply is ready.
□
9) Visual inspection:
– No badly affixed or damaged components
– No foreign objects left in the cabinet
– No dirt, dust or moisture in the cabinet
□
7.6.2. Electrical installation checklist
1) Types and cross sections of control cables suitable for the signal type 
and signal level.
□
2) Types and cross sections of power cables selected according to the ABB 
power cable specification.
□
3) Pulse encoder cable shields are connected to the shield earthing point 
and not connected directly to the pulse encoder interface (applies only to 
drives with pulse encoder interface).
□
4) Cable entries prepared according to the instructions in this user manual 
(3BHS212794 E01 N).
□
5) Control cable screens and conductors are connected as instructed in this 
user manual (3BHS212794 E01 N), labeled appropriately, and the 
customer side connections are completed.
□
6) Heating cables (if supplied) is installed according to the instructions in 
this user manual (3BHS212794 E01 N).
□