COMMISSIONING
PRODUCT
ACS6000
DOCUMENT KIND
User manual
DOCUMENT ID.
3BHS212794 E01
REV.
N
LANG.
en
PAGE
160/266
7.6.5. Motor checklist
1) Motor is installed, aligned and alignment protocol available.
□
2) Motor is not coupled to driven load.
□
3) Grounding is completed
□
4) Motor auxiliaries (eg, bearing lubrication) are ready
□
5) Control and monitoring signals are connected.
□
7.6.6. Insulation tests checklist
1) Insulation of the cables to input transformer, from input transformer to
drive and from drive to motor is tested, and measured values within
required limits.
□
2) Test report is available
If the commissioning personnel carry out the test, an additional day per
drive-motor combination must be reserved. After the test, the mains
cables can be connected, except at the drive end. Test must comply with
the specification.
□
7.6.7. Power checklist
1) Medium voltage available for startup of drive.
□
2) Low voltage is available for startup of drive.
□
7.6.8. Miscellaneous checklist
1) Sufficient number and correct type of spare parts available
□
2) Sufficient quantity of deionized water according is available. (see
“Appendix C - Mechanical drawings”).
□
3) Air conditioning of drive room ready for load run of drive
□
4) Optional equipment (eg, chiller) ready
□