Section 2 — Installation
2-20 Part No. 750-363
The neutralization media will require periodic
replacement, to be determined by pH analysis of
condensate. If condensate is too acidic (pH is below
acceptable value) the neutralization media should
be replaced.
The number of condensate treatment tanks required
depends on the total amount of condensate
produced by the system. As a general rule, CB
recommends one tank per boiler for sizes 4,000 -
8,000 and two tanks for sizes 10,000 - 12,000.
Figure 2-11 Condensate Treatment Tank - external
Figure 2-12 Condensate Treatment Tank - internal
SIZE 6000-8000
SIZES 10,000-12,000
Table 2-8 CFLC Max Condensation
CFLC Model BTU/hr
Max.
Condensation
GPH
4000 4,000,000 27
5000 5,000,000 34
6000 6,000,000 41
8000 8,000,000 54
10000 10,000,000 68
12000 12,000,000 82