990DSL
Users Guide
4-68
• Tip, Ring, Loop and Ground Resistance
• Resistive Unbalance
• 10-Tone Slope (TN2000 Terminator, FED
™
, FEDII
™
, and Helper
™
)
• SmartTone Loss & Slope (TN2100 Terminator or TN2200 Terminator II)
Setting Up a Terminated VF Test
To set up a test, complete the following:
1. Set the Pass thresholds for each individual test (see previous list).
2. Set up the Auto-Test. Do the following:
a) From the POTS Toolbox, select
Terminated VF Tests and press L.
b) From the
Select Terminated Test Type screen, press D(Setups).
c) Enter a setting for Loop Resistance, Ground Resistance, and
Unbalance Resistance Pass Thresholds.
Running a Terminated VF Test
This procedure shows you how to run a Terminator VF Auto-Test. You
can use this procedure to run the Terminated VF Test with any of the
other far-end devices listed.
To run a Terminated VF Test, do the following:
1. From
Select Terminated Test Type, press A(Terminator VF Auto-Test).
The Terminator VF Auto-Test connection diagram is displayed as shown
in Figure 4-33: