9.4 Message Reference
156
Sets and Queries the ramp-up time for withstand-voltage tests
Syntax
(Command)
:CONFigure:WITHstand:UTIMer <0.1 to 99.9 (NRf)>
Sets the ramp-up time (unit: s) for withstand-voltage tests in the
READY state.
(Query)
:CONFigure:WITHstand:UTIMer?
Queries the ramp-up time (unit: s) for withstand-voltage tests.
(Response)
<0.1 to 99.9 (NR2)>
Example
(Command)
:CONFigure:WITHstand:UTIMer 10.0
Sets the ramp-up time for withstand-voltage tests at 10.0 s.
(Query)
:CONFigure:WITHstand:UTIMer?
(Response)
10.0
The set ramp-up time is 10.0 s.
Error
The execution of this command in a state other than the READY state or "test set-
ting state" causes an execution error.
Sets and Queries the ramp-down time for withstand-voltage tests
Syntax
(Command)
:CONFigure:WITHstand:DTIMer <0.1 to 99.9 (NRf)>
Sets the ramp-down time (unit: s) for withstand-voltage tests in the
READY state.
(Query)
:CONFigure:WITHstand:DTIMer?
(Response)
<0.1 to 99.9 (NR2)>
Queries the ramp-down time (unit: s) for withstand-voltage tests.
Example
(Command)
:CONFigure:WITHstand:DTIMer 5.0
Sets the ramp-down time for withstand-voltage tests at 5.0 s.
(Query)
:CONFigure:WITHstand:DTIMer?
(Response)
5.0
The set ramp-down time is 5.0 s.
Error
The execution of this command in a state other than the READY state or "test set-
ting state" causes an execution error.