Mounting and Commissioning 3
This chapter is intended for experienced commissioning staff. They should be familiar with the commissioning
of protection and control equipment, with operation of the power system network and with the safety rules and
regulations. Certain adaptations of the hardware to the power system specifications may be necessary. For
primary testing, the object to be protected (generator, motor, transformer) must be started up and in put into
service.
3.1 Mounting and Connections 362
3.2 Checking Connections 390
3.3 Commissioning 400
3.4 Final Preparation of the Device 449