Configuration Menu
16.14 Direct Marketing
Note!
With the amendment of the German Renewable Energy Act (EEG 2014), direct marke-
ting is required for all new plants with an output greater than 500 kW.
Starting 01 January 2016, the requirement applies to all plants with an output greater
than 100 kW.
An interface has been implemented with firmware version 3.3.0 (extra license required)
for the simple, efficient and secure communication
between the the direct marketer and the remote controlled photovoltaic plant. The So-
lar-Log™ with the firmware version 3.3.0 or newer fulfills the requirements to receive the
management bonus for remotely controlled plants.
Secure data communication between the and direct marketer is mandatory. This has
been implemented with VPN encryption (VPN router).
Note!
A VPN router is required to be able to use the direct marketing function.
The Direct Marketing function is not enabled by default. To use this function the license key has to be ente-
red in the
Configuration | System | Licenses menu.
The following providers are available:
•
Energy & Meteo
•
Next Kraftwerke (Firmware 3.4.0)
Energy & Meteo / Next Kraftwerke
Direct marketing via
Energy & Meteo or Next Kraftwerke is carried out using remote control options.
The following remote control options are available:
•
Modbus
•
Ripple Control Receiver
•
Ripple control receiver with consideration of self-consumption
We offer different license models via a corresponding license key.
The following license options are available:
•
Plant size to 100 kWp
•
Plant size to 500 kWp
•
Plant size to 1 MWp
•
Plant size to 2 MWp
•
Plant size to 5 MWp
•
Plant size to 10 MWp
•
Plant size to 20 MWp