126 Operation Manual
Liner O-ring Number of injections 1000
Liner O-ring Time 60 days
Septum Number of injections 200
Split vent trap Number of injections 10,000
Split vent trap Time 6 months
Cooling cycles Number of injections
Clean bottom seal Number of injections 1000
PP Liner Number of injections 200
Liner Time 30 days
Septum Number of injections 200
Top weldment O-ring Number of injections 10,000
Top weldment O-ring Time 1 year
COC Septum Number of injections 200
PTV Column adapter silver
seal
Number of injections 5000
Liner Number of injections 200
Liner Time 30 days
Split vent trap Number of injections 10,000
Split vent trap Time 6 months
PTFE ferrule Number of injections
PTFE ferrule Time 60 days
VI Split vent trap Number of injections 10,000
Split vent trap Time 6 months
Columns
Column Injections onto
column
Number of injections
Oven cycles Number of injections
Length Value
Run count Number of runs
Valves
Valve Rotor Activations (number of
injections)
Maximum
temperature
Value
Instrument
Table 14 Common EMF counters (continued)
GC
Component
Parts with a counter Type Default value