MLC650 OPERATOR MANUAL SET-UP AND INSTALLATION
4
Install the Boom Load Lines
1. Route the load lines up the boom. See Figure 4-164 on
page 4-210.
2. Pull the load lines approximately 20 ft (6,1 m) past the
end of the boom.
3. Install the load block(s)(10) and hook-and-weight ball (7)
after the boom is raised to a convenient height. See
Boom Raising Procedure on “Boom Raising Procedure”,
on page 4-126.
If equipped, the rigging winch can be used to assist in
pulling the load lines. See "Rigging Winch Operation" on
page 4-208.
4. Read the following topics:
"Wire Rope Installation" on page 4-201
.
"Load Line Reeving" on page 4-211
.
"Wire Rope Specifications" on page 4-212
.
Reeving diagrams at the end of this section
Install the Boom Block-Up Limit
Components
Install the block-up limit components as shown in
Figure 4-101
. The chains (14, stored) and weights (15,
stored) are shipped on the top and the point.

Table of Contents

Other manuals for Manitowoc MLC650

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc MLC650 and is the answer not in the manual?

Manitowoc MLC650 Specifications

General IconGeneral
BrandManitowoc
ModelMLC650
CategoryConstruction Equipment
LanguageEnglish

Related product manuals