Ascotel IntelliGate 2025/2045/2065
Part 3 Planning DECT systems 635
Fig. 3.31: Determining locations
5.4.4 Installing and re-measuring the definitive system
For more detailed information, please refer to Part 4.
As soon as the definitive system is installed, test measurements should be carried
out in handover overlap border areas and compared with the results of the plan-
ning (see "On-site measuring", page 626). Critical areas should be discussed with
the customer.
5.5 Measuring Equipment
The test kit contains the following equipment:
• Two test radio units with integrated charging bays for the handsets
• 2 test handsets for the test radio units
• 2 standard handsets (with Foxkeys)
• 1 set of Operating Instructions - Planning
• 1 set of Operating Instructions for the standard handset
• 1 set of Operating Instructions for the test handset
• 40 batteries
• 2 charging units
• 2 battery boxes for the radio units
• Miscellaneous cables
haz0334aaxxa0