20 of 220 Instrument Installation - Anatel A643a
RPS - June 2007 - Edition 12
Operator Manual Anatel
2.2 Pre-Installation Procedures
Preliminary setup procedures should be conducted on the Anatel A643a components prior to
installing them on the water system to help assure their proper operation. Verification also is
easier at this stage than when the components have been mounted and cabling has been run.
Suggested pre-installation procedures are:
• Unpacking, visually inspecting the equipment and verifying the packing list.
• Powering up the Analyzer to verify that all the components are operational (refer to
“Specifications and Accessories” on page 191 for the specific power requirements of
each component).
• Setting up the operational software by entering the System Time and naming the
Analyzer.
Note:
The terms “Anatel A643a” and “Analyzer” refer generally to all A643a TOC Analyzer models.
2.2.1 Unpacking & Inspection
Upon receiving the Anatel A643a Analyzer, inspect the shipping container(s) for any signs of
external damage before unpacking the components. Carefully remove the equipment, verify
the enclosed packing list and check once again for obvious damage.
Each Anatel A643a Installation Kit contains:
• Power Cord
• Network “Tee” & Terminator
• 15 Micron Inlet Filter
•
5’ 1/4” OD Sample Tubing
• 1
0’ 1/8” OD Drain Tubing
• 1/4” Tube x 1/4” MNPT Fitting
• Operator Manual and Standard Operating Procedures (SOPs)
If damage is apparent, notify the freight carrier immediately: Claims must be filed by the
customer. Also notify Hach Ultra or your distributor of any such problems. Include the Serial
Number of the damaged unit(s) and your purchase order number with all factory
communications.
2.2.2 Operational Verification
The next pre-installation step is to establish communication connections between the C80
Controller and its associated Anatel A643a–S Analyzer (these connections are internal to the
Anatel A643a–P).
Each Anatel A643a–S Analyzer and C80 Controller is supplied with a 3-foot local cable, a twin
BNC “tee” connector, and a passive terminator. The C80 Controller also includes a 10-foot
trunk cable to facilitate communications connections.
Note:
Additional twin-axial trunk cable, pre-wired with BNC plugs at each end, is available from Hach
Ultra in 10-, 25-, 50-, 100-foot and custom lengths.