2.11 V3 BBU WALL MOUNTING
If applicable, drill eight holes on the wall using the position of eight holes on the BBU mounting bracket
as a guide (BBU mounting bracket is built into the BBU cabinet).
This step will require two people or special lifting equipment. Lift the BBU cabinet (Without Batteries)
into position and install the cabinet on the wall. It is recommended to use 3/8” x 1-1/2” lag screws and
fender washers when mounting to 3/4” fire treated plywood. If mounting to a concrete wall, DIN Rails, or
any other materials, refer to the local building code. Secure the BBU.
Figure 30: V3 BBU Wall Mounting
(8) 3/8'' x 1-1/2'' Lag Screws
and Washers for plywood