13 Measurement support
13.1 Use Smart Meter Verification
Smart Meter Verification (SMV) provides in-process flow meter health verification by analyzing the meter
components related to measurement performance. You can run Smart Meter Verification without stopping
the process. Use this section to run a Smart Meter Verification test, view and interpret the results, set up
automatic execution, and check if a field reference point has been established.
13.1.1 Smart Meter Verification capabilities
Capability
Basic Professional
Included 90-day trial, licensed
Calibration coefficients audit ● ●
Zero audit ● ●
Electronics verification ● ●
Automatic test scheduler ● ●
History of previous 20 results ● ●
Verification report ●
(1)
(1) Create and export with ProLink III, or AMS SNAP-ON.
13.1.2 Setting the field reference point using the display
Prerequisites
Read the Smart Meter Verification prerequisites in Use Smart Meter Verification.
Procedure
Choose Menu → Operations → Smart Meter Verification → Set Field Reference Point.
13.1.3 Setting the field reference point using the ProLink III
Prerequisites
Read the Smart Meter Verification prerequisites in Use Smart Meter Verification.
Procedure
Choose Device Tools → Diagnostics → Meter Verification → Set Field Reference Point.
Important
Ensure the meter is full of single-phase fluid at normal operating conditions before establishing the Reference
Point. If the Field Reference Point was not run at operating conditions, it may not be appropriate for the
process.
NOTICE
Do not overwrite an existing Field Reference Point if the meter has been installed for a long period of time, or
if there is a chance of corrosion, erosion, or other tube damage.
Configuration and Use Manual Measurement support
MS-00809-0200-1600 May2024
Configuration and Use Manual 137