Runtime Actions SECTION 9 Animation
139
9-3-11 Vertical Percentage Fill
Closed objects can be flood-filled along a vertical axis. This can be specified
via the Percentage Fill (Vertical) dialog box.
To access the Percentage Fill (Vertical) dialog box to add an action, select
Percentage Fill (Vertical) from the animation list and click the Add Action
button. To access the Percentage Fill (Vertical) dialog box to modify an action,
select Percentage Fill (Vertical) from the animation list and click the Modify
Action button. Refer to chapter 9, Objects, for a list of the objects to which this
action is applicable.
On selection of the Percentage Fill (Vertical) action, the Percentage Fill
(Vertical) dialog box opens:
To define the animation, an expression consisting of a number of operators
and operands, which may be based on the status of a point, must be entered
in the Expression: field.
The boundaries in which the object moves are inserted into the Active
Expression Range/Required Percentage Fill: fields. The % Filled fields specify
the percentage of the object to fill when the expression reaches its maximum
and minimum values. The flood-fill also requires a direction. This can be
specified as top to bottom or bottom to top, by selecting the appropriate Fill
Direction: setting.
To abort the Vertical Percentage Fill definition, click the Cancel button. By
clicking the Browse button, a point may be directly specified, as described in
chapter 9, Runtime Actions. When completed, click the OK button. If invalid
data has been inserted into any field, a descriptive error message opens.
9-3-12 Display Page
CX-Supervisor allows the specification of pages within a project for display.
This is set up using the Display Page dialog box.
To access the Display Page dialog box to add an action, select Display Page
from the animation list and click the Add Action button. To access the Display
Page dialog box to modify an action, select Display Page from the animation
list and click the Modify Action button. Refer to chapter 9, Objects, for a list of
the objects to which this action is applicable.
On selection of the Display Page action, the Display Page dialog box opens:

Table of Contents

Other manuals for Omron CX-Supervisor

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Omron CX-Supervisor and is the answer not in the manual?

Omron CX-Supervisor Specifications

General IconGeneral
BrandOmron
ModelCX-Supervisor
CategorySoftware
LanguageEnglish

Related product manuals