9.2 Series commissioning using the web server
Requir
ement
• The machines that are commissioned via series commissioning are identical in terms of the
application, converter and motor.
Procedure
Proceed as follows to perform series commissioning using the web server:
1. Switch on the converter supply voltage and use your operating unit, e.g. a PC, to perform
commissioning.
You can nd more information in Chapter "Commissioning (web server) (Page163)".
2. Save the settings at the end of commissioning.
3. Select "Backup and Restore" in the navigation - and back up the parameter settings in a le
using "Back up parameters".
4. Connect your operating unit to the next converter.
5. Switch on the supply voltage to the converter.
6. Enter the IP address of the converter, e.g. https://169.254.11.22, in the browser.
7. Select the option "Exit the Security Wizard and continue with low security settings".
User management and access control (UMAC) is not activated.
You can congure the security settings at a later time, see Chapter "Protection & Security
(Page211)".
8. In the navigation, select "Backup and Restore" - and load the parameter settings using
"Restore drive data from backup le" to the converter.
The converter accepts the parameters (including from user management and access control)
from the le and restarts.
Repeat steps 4to7 for all converters to which you want to transfer these settings.
Series commissioning
9.2Series commissioning using the web server
SINAMICS S200 PROFINET servo drive system with SIMOTICS S-1FL2
Operating Instructions, 11/2023, FW V6.3, A5E51646752B AB 317