3. On the Start Service Tools Sign On display, type in a User ID with QSRV
authority and Password.
4. Select the Start a service tool option.
5. Select the Hardware service manager option.
6. Select the Logical hardware resources option.
7. Select the System bus resources option.
8. Page forward until you find the multi-adapter bridge where the problem was
reported. For help in identifying the multi-adapter bridge from the Direct
Select Address (DSA) in the SRC, see Hardware SRC Formats on page 940.
Verify that the multi-adapter bridge is the correct one by matching the
resource name on the screen with the resource name in the Service Action Log
(SAL) for the problem that you are working on.
9. Select the Include non-reporting resources function.
10. Move the cursor to the first IOP under the multi-adapter bridge.
11. Select the Associated packaging resource(s) option for each IOP that is under
the multi-adapter bridge that you are working on.
12. Select the Display detail option.
13. Record the location of the I/O processor (IOP).
14. Select cancel.
15. Select cancel again.
16. Select the Resources associated with IOP option.
17. For each I/O adapter under the IOP, perform the following:
a. Select the Associated packaging resource(s) option.
b. Select the Display detail option.
c. Record its location.
18. Power off the frame or tower (see Powering On and Powering Off the
System and Logical Partitions on page 922).
19. Remove one of the IOPs and all of its IOAs.
20. Power on the frame or tower (see Powering On and Powering Off the
System and Logical Partitions on page 922).
21. Check for the same failure which brought you to this procedure. Check the
system control panel, the Service Action Log (SAL) for the partition which
reported the problem, or the Work with partition status screen for the partition
that reported the problem.
22. Did the same SRC appear after the frame or tower was powered on?
Yes No
Go to step 27 of this procedure.
23. Power on the frame or tower.
24. Return to the System bus resources screen showing the multi-adapter bridge
and the associated resources.
25. Is there another IOP under the multi-adapter bridge?
No Yes
Go to step 18 of this procedure.
26. Go to step 30 on page 317 of this procedure.
27. Failing IOP located - The failing item is either the I/O processor or one of the
I/O adapters that it controls. Reinstall the IOP and I/O adapters that you just
removed. Perform BUS PIP BUS PIP IOP-02, Isolate to Failing I/O Adapter
Bus, High-Speed Link (HSL) PIPs
316
iSeries Model 830, 840, SB2, and SB3 Problem Analysis, Repair and Parts V5R1

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM i 830 and is the answer not in the manual?

IBM i 830 Specifications

General IconGeneral
BrandIBM
Modeli 830
CategoryServer
LanguageEnglish

Related product manuals