Page 191
STAT
IM
2000/2000S Service Guide
96-108639 Rev 3.0
8. Water Pumps, Reservoir, and Compressor
STATIM 2000/2000S/2000 G4 Service Guide
Reinstalling the Compressor
To reinstall the compressor, proceed as follows (see Figure 24):
1. Route the ground wire (12) with the wiring harness leading to the controller board and connect
it to the ground post (13).
2. Reinstall the rubber compressor mounts (11) in the chassis using the four screws (10) retained
during disassembly. Apply a small amount of Locktite™ to the threaded holes in the chassis.
3. Route the compressor leads (8) with the wiring harness leading to the controller board (9).
Secure the leads and ground wire using nylon cable ties every 2-3 inches. Connect the black
wire to controller board terminal block position J1-9 LINE and the white wire to terminal block
position J1-10 NEUTRAL.
4. For units with the compressor air filter only:
a. Connect the silicone rubber tube (1) which extends from the steam generator check valve
(3) to the top of the compressor (2). Secure the tube using a cable tie (4).
For units with the additional bacteria-retentive filter (see Figure 24):
b. Connect the silicone rubber tube (5) which extends from the input side of the bacteria-
retentive filter (7) to the top of the compressor (2) and secure the tube using a cable tie (4).
If the tube from the check valve fitting was disconnected, re-attach and secure the tube
using a high temperature rated cable tie)
5. Test the compressor by activating the compressor with the control box or keypad as
appropriate.
6. A dielectric strength test (Hi-Pot) AND a protective bonding impedance test (ground continuity)
must be performed on the STATIM when the work is completed and after the cover has been
returned to the unit.