13. Installation
If the integrator shows a fail, do not use the unit. Replace unit and call SciCan representative.
3. TESTING THE UNIT
Power up unit and run as follows:
Check cycle selection on all cycles.
Assemble test helix and integrator as per helix instructions. (S units only).
Remove cassette and place assembled helix on instrument rack.
Insert cassette and run a Hollow Wrapped Cycle (S units)/ Wrapped cycle (non S units).
Check for steam leaks
At end of cycle, (no drying) remove cassette and remove helix.
Check integrator for pass/fail ( = pass = fail)* (S units only)
Run 2nd Hollow Wrapped/Wrapped cycle