Common Problems and Solutions Troubleshooting
454 U41840-J-Z125-7-76
Replication Problems
Table 25 describes corrective actions for problems occurring with the replication.
Table 25: Replication Problems
Problem Explanation/Corrective Action
The replication was paused, but
the replication is still in process.
When you click Pause, the system will continue to
replicate the current tag or block of information in
process. The process of completing the current tag
replication can take up to 15 minutes to complete.
Once that tag has completed replication the system
will pause and wait to resume.
The replication was paused and a
Failure event was generated in the
Replication Events page.
This is normal. When a replication is paused, a
failure event is generated on the Replication
Events page. They system will continue the repli-
cation when you click Resume.
Replication was disabled while a
replication was in process and the
replication completed.
If you click Disable during a replication in process,
the system will complete the entire replication and
then disable replication on the system. The system
will be unable to replicate until you click Enable.
Enabled replication on a NAS
share and received the following
Event: No destination host is
specified for replication.
You must configure the target system prior to config-
uring the source. If the target system is not
configured first, you will not be able to designate the
replication target.
Replication for NAS can be
enabled and scheduled even
though no target IP is configured.
It is possible to enable and schedule a replication
when a target system has not been configured. The
replication will not start until a target system is
configured.