IRECTION 5344303-100, REVISION 3 VIVID P3 SERVICE MANUAL
3-12 Section 3-5 - Completing the Installation
2.) The System-Exit window is displayed.
3.) Using the Trackball or Select key, select Shutdown.
4.) The shutdown process takes a few seconds and is complete when the power status LED is turned
Amber color.
5.) Disconnect the probes.Clean or disinfect all probes as necessary. Store them in their shipping
cases to avoid damage.
3-5-2-2 Scanner Shutdown
1.) Switch OFF the Circuit Breaker at the back of the system.
2.) Disconnect the Mains Power Cable if necessary. For example: Relocating the scanner.
Figure 3-7 System Exit Window