Unpacking and Preparation
Checking the Shipment
1-
Checking the Shipment
After you receive the E4980A/AL, carry out checks during unpacking according 
to the following procedure.
Step 1. Check that the packing box or shock-absorbing material used to package the 
LCR meter has not been damaged.
Step 2. Check the packaged items supplied with the LCR meter for any damage or 
defects.
Step 3. Referring to 
Table 1-1 and Figure 1-1, check that all packaged items supplied 
with the LCR meter have been provided as per the specified options.
Step 4. After checking, if one of the following applies, contact your nearest Keysight 
Technologies sales and service office.
1. The packing box or shock-absorbing material used to package the LCR 
meter has been damaged or the shock-absorbing material displays traces 
of where extreme pressure has been applied.
2. A packaged item supplied with the LCR meter has mechanical damage or 
defects.
3. A packaged item supplied with the LCR meter is missing.
4. A fault has been detected in the subsequent operation check of the LCR 
meter. 
If an abnormality is detected in Step 1, contact the company that transported 
the LCR meter as well as your nearest Keysight Technologies sales and 
service office. For inspection by the transport company, save the packing box, 
shock-absorbing material, and packaged items as you received them.
If the external face of the LCR meter (such as the cover, front/rear panel, 
LCD screen, power switch, and port connectors) appears to have been 
damaged during transport, do not turn on the power switch. Otherwise, 
you may get an electrical shock.
If the packing box or shock-absorbing material has been damaged, leave 
the packing box and shock-absorbing material as is until other inspection 
items are checked as follows: