Points to Note About Turning Off the Main Power Switch
This equipment does not have a main power switch, but it has only a leakage breaker.
This equipment is powered when the main power switch of the host machine is turned on.
The leakage breaker detects overcurrent and power leakage.
NOTE:
Explain to the customer that the leakage breaker must be checked once or twice a month and the result must be recorded.
Points to Note Before Servicing
• At servicing, be sure to turn OFF the power source according to the specified steps and disconnect the power plug.
• At the time of assembly and disassembly, be sure to place a sheet of paper under the parts to prevent them from being soiled
or foreign matter from entering the parts.
• Before installing the parts to the host machine, ensure that they are free of foreign matter.
• Be careful not to be injured by burrs of edges, sharp corners or protrusions.
CAUTION:
Hazardous area such as corners, edges, springs and other sharp sections may be remaining on products. Always be
aware of the presence of hazardous area to avoid injury caused by contacting and/or striking those area, by not over-
concentrating on service work.
Safety Precautions