CHAPTER 6
Preparation Overview
Site Preparation Checklist for EX4550 Switches on page 71
Environmental Requirements and Specifications for EX Series Switches on page 72
General Site Guidelines on page 76
Site Electrical Wiring Guidelines on page 77
Chassis Physical Specifications for EX4550 Switches on page 79
Rack Requirements for EX4550 Switches on page 79
Cabinet Requirements for EX4550 Switches on page 80
Clearance Requirements for Airflow and Hardware Maintenance for EX4550
Switches on page 81
Site Preparation Checklist for EX4550 Switches
The checklist in Table 39 on page 71 summarizes the tasks you need to perform when
preparing a site for EX4550 switch installation.
Table 39: Site Preparation Checklist
DatePerformed byFor More InformationItem or Task
Environment
“Environmental Requirements and
Specifications for EX Series
Switches” on page 72
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure the distance between external power
sources and the switch installation site.
Locate sites for connection of system
grounding.
AC Power Supply Specifications
for EX4550 Switches on page 85
DC Power Supply Specifications
for EX4550 Switches on page 88
Calculate the power consumption and
requirements.
71Copyright © 2015, Juniper Networks, Inc.

Table of Contents

Other manuals for Juniper EX4550

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Juniper EX4550 and is the answer not in the manual?

Juniper EX4550 Specifications

Console Connection Settings IconConsole Connection Settings
baud rate9600
data bits8
stop bits1

Related product manuals