2.3.1 575V Inverter - DC Reactor Installation
For 575V inverters (7.5 HP ~ 40 HP), a DC Reactor is supplied mounted in a conduit box. It requires
mounting and connection to the inverter. Follow the steps below to install and connect the DC
Reactor.
7.5 HP ~ 40 HP
a. Remove the Terminal cover from the
inverter.
b. Remove the Cable Guide/Bracket from
the inverter.
c. Remove the top cover of the DC
Reactor/Conduit Box.
d. Mount the DC Reactor/Conduit Box to
the inverter.
e. Remove the Jumper (Shorting Bar)
from terminals P1 and P2.
f. Connect DC Reactor wires to terminals
P1 and P2.
g. Reinstall the Cable Guide/Bracket.
h. Inverter can be mounted at this time.
i. Complete the remaining Power wiring.
j. Complete the Control wiring.
k. Reinstall the Terminal cover.
l. Install the top cover of the DC Reactor/Conduit Box.