142 of 282 M-SV-001-EN Rev. G
Figure 4-156 Fuse Block Assemblies - Two Hole Mount - TTS300/TGS230
6. Remove the bolts that secure the (+) and (-) SCR Bus Bars to the DC Bus Bars. Refer to "Figure
4-157 DC Bus Bar Removal - TTS300/TGS230" and "Figure 4-158 SCR Removal - TTS300/TGS230"
on page 143 for this and the following two (2) steps.
7. Remove the six (6) M6x16 fasteners that secure the (+) and (-) SCR Bus Bars to the SCRs.
8. Remove the DC Bus Bars.
Figure 4-157 DC Bus Bar Removal - TTS300/TGS230
9. Remove the two (2) M6x16 fasteners that secure each SCR to the SCR Cooling Manifold and
remove the SCRs. "Figure 4-158 SCR Removal - TTS300/TGS230" on page 143 for this and the
following step.
AC Bus Bar to SCR
Fastener, M6x16
(3 places)
Fuse to Terminal
Block Fastener
(6 places)
SCR Gate
Connectors
(6 places)
Mylar
SCR Bus Bar
Fastener, M6x16
(6 places)
DC Capacitor Bus Bar
to SCR Bus Bar Bolt/
Nut, M6