M-SV-001-EN Rev. G
Chapter 6.0 Maintenance
6.1 Preventative Maintenance Tasks
"Table 6-1 Preventative Maintenance Tasks" identifies tasks that should be performed on a regular
basis to maintain optimal performance of the system.
Table 6-1 Preventative Maintenance Tasks
Item Task
Frequency
6 Mos 12 Mos Other
General
Inspections
Check physical condition of compressor. √
Check for excessive vibration from other rotating equipment. √
Check for oil in the system. The compressor must operate in an oil-free environment. Ensure all
oil is removed from the system.
√
Compressor
Inspections
Connect to the compressor using the Service Monitoring Tools software and download fault
and event logs. Review and save logs for future reference.
√
Connect to the compressor using the Service Monitoring Tools software and perform a
calibration. Do not save the calibration to EEPROM if the compressor has been operating
correctly. Create and save a Calibration Report for future reference.
√
Electrical
Inspections
Check main power supply voltages. √
Ensure electrical terminals are tight. √
Check for signs of hot spots/discoloration on power cables. √
Check amperages during operation are as per design. √
Check DC bus voltage. √
Replace DC Capacitor Bus Bar Assembly.
Energized:
10 years
De-
energized:
5 years
Check operation of all system safety devices and interlocks. √
Perform moisture-prevention measures. √
Replace Soft Start fan.
5 Years, Refer
to Customer
Notification
B-CN-041-EN
Electronic
Inspections
Ensure all communication cables are secure. √
Ensure all electronic modules are secure. √
Check physical condition of all exposed PCBs. √
Check all exposed PCBs for dust build-up and clean if necessary. √
Check discharge and suction pressure/temperature sensors for accuracy against calibrated
pressure/temperature gauges.
√
Refrigeration Check operation of IGV assembly. √
Check system refrigeration charge. √
Check superheat/level control, if applicable. √
Check system and motor-cooling liquid line to ensure sufficient sub-cooling. √
Verify discharge check valve operation.
If there is backward gas flow immediately after stopping the compressor, replace the check
valve.
√
Check operating conditions external to the compressor. √
Inspect/clean motor-cooling strainer (if service has taken place). As required

Table of Contents

Other manuals for Danfoss Turbocor TTS Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Danfoss Turbocor TTS Series and is the answer not in the manual?

Danfoss Turbocor TTS Series Specifications

General IconGeneral
BrandDanfoss
ModelTurbocor TTS Series
CategoryCompressor
LanguageEnglish

Related product manuals