Operation
182
Pos: 32.10 /BA/Bedienun g /Großpackenpresse/ Ballenausschi eberAusschieben des let zten Ballens T1 @ 20\mod_1238 663580850_78.doc x @ 224502 @ @ 1
10.6 Ejection of the last bale
Before ejecting the last bale it should be tied up. To do this, initiate the tying process manually
(refer to chapter “Initiating the tying process manually” with medium design) or (chapter Manual
mode basic screen 2/2 “Knotter triggering”).
10.6.1 Opening the bale channel chamber
Afterwards, open the bale channel chamber.
To this:
10.6.1.1 Medium design:
Fig. 117
Note
The shut-off valve (1) is used to release the bale channel chamber.
The machine is in the working position in setting (a). To release the bale channel chamber, use
position (b) (tank return). If the shut-off valve is in position (b), it is not possible to build up
pressure.
• Bring shut-off valve for releasing the bale channel chamber in position (b)
10.6.1.2 Comfort design:
In the case of the comfort design, this function can be switched from the control unit or on the
machine keys (see chapter Manual mode basic screen 2/2).