Issue 9 October 1998
3-1
Lucent Technologies
3
Equipment and Front Access Cable
Installation
Overview
This section provides the information for front access installation and covers the
installation information for the shelf, heat baffles, fans, front access cables, and
grounding.
This installation manual contains the latest cable information at the time of issue.
For up-to-date information, refer to the ED cable drawings listed in the "About This
Document" section. For miscellaneous equipment information, refer to
"Miscellaneous Equipment" in the section "Introduction".
Description
Procedures in this section should be performed on all front access shelf
installations. For rear access installations, refer to the "Equipment and Rear
Access Cable Installation" section of this manual. Observe the following notes:
NOTE
:
This section requires previous bay frame installation and grounding. The
shelf should be grounded by its mounting screws.
NOTE
:
It is important to carefully follow the procedures in this section to ensure
that the bay will accommodate all of the cables and that the backplane
cover will fit properly.
NOTE
:
It is recommended that ONLY designated Lucent Technologies cables be
used.