6-20
Issue 9 October 1998
363-206-204
Release 7 Installation Tests
Final Operations
Procedure
1. Verify that all test signals and loopbacks from the DDM-2000 OC-3 have
been removed.
2. Press the UPD pushbutton on the SYSCTL.
3. Verify that the system is configured for normal operation and that no alarms
are present
4. If alarms (other than BBG6 alarms as previously described) are present,
refer to the Troubleshooting" section of this manual.
5. Connect the office alarm cables if they have been disconnected.