19.10.4 Procedure for executing the WORK DATUM setting cycle
1. Set the orange keyswitch to position 3 on the MCP
2. Select [JOG] mode on the MCP
3. Load the Work Datum setting cycle [Custom > Matrix > Main Menu > Setting Cycles > Set
Work Datums]
4. Using handwheel or JOG buttons [+][-] manually position the grinding wheel to the start grind
position.
5. Press [Set Z Start Pos] softkey to store the Z start grind position value to memory.
6. Now use handwheel or JOG buttons [+][-] manually position the grinding wheel to the end
grind position.
7. Press [Set Z End Pos] softkey to store the Z end grind position value to memory.
8. Work datum setup complete!