Commissioning
5.2 Preparing for commissioning
Inverter with CU230P-2 Control Units
74 Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
5.2
Preparing for commissioning
Overview
Before starting commissioning, you must know the answer to the following questions:
Inverter
What are the data specifications of my inverter?
Identifying the converter (Page 25).
What inverter interfaces are active?
Wiring examples for the factory settings (Page 75).
How is the inverter integrated in the higher-level control system?
How is my inverter set?
Factory setting of the converter control (Page 77).
What technological requirements must the drive fulfill?
V/f control or vector control (speed/torque)? (Page 78).
Defining additional requirements for the application (Page 79).
Motor
What motor is connected to the inverter?
If you are using the STARTER commissioning tool and a SIEMENS motor, you only need
the motor order number. Otherwise, note down the data on the motor rating plate.
In which region of the world will the motor be used?
- Europe IEC: 50 Hz [kW]
- North America NEMA: 60 Hz [hp] or 60 Hz [kW]
How is the motor connected?
Pay attention to the connection of the motor (star connection [Y] or delta connection [Δ]).
Note the appropriate motor data for connecting.
What is the motor ambient temperature?
For commissioning you need the motor ambient temperature if it differs from 20 °C.