Inverter with CU230P-2 Control Units
Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
73
Commissioning
5
5.1
Commissioning guidelines
Procedure
Proceed as follows to commission the inverter:
1.
Define the requirements of
your application placed on
the drive.
(Page 74).
2.
Reset the inverter when
required to the factory
setting.
(Page 79).
3.
Check whether the factory
setting of the inverter is
appropriate for your
application.
If not, start with the basic
commissioning.
(Page 80).
4.
Check whether you need to
adapt the functions of the
terminal strip that you
specify in the basic
commissioning.
(Page 93).
5.
If necessary, adapt the
communications interface in
the inverter.
(Page 107).
6.
If necessary, set further
functions in the inverter.
(Page 225).
7.
Save your settings.
(Page 323).
You have commissioned the inverter.