Commissioning
5.4 Basic commissioning
Inverter with CU230P-2 Control Units
80 Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
Basic commissioning
5.4.1
Basic commissioning with the BOP-2 operator panel
To do this, insert the Basic Operator Panel BOP-2 on the Control Unit of the inverter.
Proceed as follows to install the BOP-2 operator panel:
Locate the lower edge of the BOP-
2 housing into the matching recess
of the Control Unit.
Press the BOP-2 onto the inverter until you hear the latching
mechanism engage.
The BOP-2 operator panel is ready for operation when you connect the inverter to the power
supply.
Setting the basic commissioning data
Basic commissioning is the first step of the commissioning procedure. The BOP-2 Operator
Panel guides you through the basic commissioning process and prompts you to enter the
most important data for your inverter.
BOP-2 Operator Panel on the inverter and
connected the inverter to a power supply.
The Operator Panel has powered up and displays setpoints and actual
values.