Commissioning
5.4 Basic commissioning
Inverter with CU230P-2 Control Units
84 Operating Instructions, 11/2013, FW V4.6.6, A5E02430659B AG
● In the basic commissioning, you have selected the motor identification (MOT ID). In this
case, after the basic commissioning has been completed, the inverter issues the alarm
A07991.
You can recognize an active alarm from the corresponding symbol on the
BOP-2.
● The motor is cooled down to the ambient temperature.
If the motor is too hot, the motor data identification will provide incorrect values and the
closed-loop speed control can become unstable.
To initiate motor data identification and optimization of the motor control, proceed as follows:
⇒
Press the HAND/AUTO key. The BOP
-2 displays the HAND
Wait until the inverter switches off the motor after completion of the
motor data identification.
The measurement takes several seconds.
Save the measurements so that they are protected
against power
If you have also selected a rotating measurement
in addition to the
motor data identification, then the inverter again issues the alarm
A07991.
Switch the motor on again in order to optimize the speed control.
Wait until the inverter switches off the motor after completion of the
o
ptimization. The optimization can take up to one minute.
Switch the inverter control from HAND to AUTO.
Save the measurements so that they are protected against power
failure.
You have now completed motor data identification and the closed-loop speed control has
been optimized.