A work bench should be installed in the separator room.
Hot water, compressed air and diesel oil should be available
near the work bench to make maintenance work easier.
An overhead hoist with capacity of 300 kg is required for
transport of bowl parts to the working bench. Lifting point should
be above the centre of the separator.
N
O
T
E
When two or more separators are installed, the
lifting height should be increased to enable bowl
parts from one separator to be lifted and moved over
an adjoining separator.