9.3 PLANNING OF INSTALLATION 9 INSTALLATION
172
9.3.3 Connections to surrounding
equipment
Local safety regulations
If the local safety regulations prescribe that the
installation has to be inspected and approved by
responsible authorities before the plant is put
into service, consult with such authorities before
installing the equipment and have the projected
plant design approved by them.
Service media
Ensure that all service media (electric power,
operating and safety liquids etc.) required for the
separator have the correct quality and capacity.
Sludge discharge tank
If the sediment from the separator is discharged
into a tank, this tank must be sufficiently
ventilated. The connection between the
separator and the tank must be of the size and
configuration specified.
If the solids are discharged from the separator
bowl casing into a closed system, ensure that
this system cannot be overfilled or closed in such
a way that the solids cannot leave the bowl
casing. This could cause a hazardous situation.
G0873911
G0874021
G0874311