9 PERIODIC MAINTENANCE DACS-W Operation Manual
9-2
9.2 Daily Inspection
9.2.1 Pre-Startup Inspection
Before starting production, perform the inspection procedure described below.
•
••
• Always turn off the power switch before performing inspection.
9.2.2 Inspection during Production
9.3 Periodic Inspection
Table 9-1 Pre-startup Inspection Checklist
Inspection Item Condition to Check Measure
Area around equipment Check that no tools or fixtures unnecessary for production
have been left on or around the checkweigher.
Remove any unnecessary
items.
Table 9-2 Inspection During Production
Inspection Item Condition to Check Measure
Belt condition Check that there is no lateral shifting in the weigh and infeed
conveyor belts.
Adjust the belt tension.9.4.3
Abnormal noise Check that there is no lateral shifting in the weigh and infeed
conveyor belts.
Check that there is correct tension in the weigh and infeed
conveyor belts.
Check whether noise is coming from rotation mechanical
components.
Consult an Ishida Service
representative.
Table 9-3 Periodic Inspection List
Inspection Item Period Inspection Item
Span adjustment Monthly Perform span adjustment. [See 5.6.3]