8 Start-up and recommissioning
8.1 Removing the transport safeguard
Precondition
The cell is upright and unpacked.
Procedure
1. Remove the lift door.
2. Unscrew 4 knurled screws.
3. Open the maintenance door and remove the PE bag.
4. Remove 4 plugs from the PE bag and insert the knurled screws into
the holes.
Fig. 8-1
1 Knurled screws
2 Plug
5. Put the knurled screws in the PE bag.
6. Remove 4 Allen screws and washers from the floor with a size 5 Allen
key and put them in the PE bag.
Fig. 8-2
8.2 Installing the ready2_educate cell
Precondition
The installation site is sufficiently lit.
The installation site is free from excessive dirt and humidity.
ready2_educate
BA ready2_educate V8 | Issued: 05.09.2018 www.kuka.com | 89/154
Start-up and recommissioning