• 6-mm hexagon Allen wrench key
• SW 12-mm single-headed wrench
• Side panel removal tool
• Keys to the front door, rear door, and side panel locks
• Cage nut mounting tool
• 32 M6 cage nuts
• 32 M6 screws
• Straight tip
3.2.5 Prepare the Installation Site
The following procedure describes how to prepare the site prior to unpacking and
situating the Exalogic machine:
1.
Thoroughly clean and vacuum the area in preparation for the installation.
2.
Note problems or peculiarities at the site that require special equipment.
3.
Verify that the installation site flooring has a strength rating to withstand the
combined weight of the Exalogic machine and any other installed equipment.
Note:
For more information, see Environmental Requirements.
4.
Install all necessary electrical equipment and ensure that sufficient power is
provided.
See Also:
The Sun Rack II Power Distribution Units User's Guide for the Sun Rack II Power
Distribution Unit (PDU) power requirements
5.
Ensure that the installation site provides adequate air conditioning.
6.
Operate the air conditioning system for 48 hours to bring the room temperature to
the appropriate level.
3.2.6 Place the Exalogic Machine in Its Allocated Space
This section contains the following topics:
• Move the Exalogic Machine
• Stabilize the Exalogic Machine
• Attach a Ground Cable (Optional)
3.2.6.1 Move the Exalogic Machine
The following procedure describes how to move an Exalogic machine:
Prepare to Install an Exalogic Machine
Install Planning and Procedure 3-5