4.10 Tests Included on the Report
When the report is generated, it can include:
•
Accepted Tests—Only tests that are acceptable according to the
Lot Limit specification at test time will be included in the report.
• Rejected Tests—Only tests that are rejected according to the Lot
Limit specification at test time will be included in the report.
• Accepted/Rejected Tests—All tests are included in the report,
whether or not they were accepted or rejected according to the Lot
Limit specification.
Accepted and rejected tests are determined by the Lot Limits as they
were at the time of testing. Properties that are rejected are shown in
bold on a report to the screen. Rejected properties are in bold and
underlined on a printed report.