Chapter 2 Installation
The HVI 900 System is shipped in three separate crates containing the
module cabinets, peripherals, and some of the internal parts of the
system. Any loss or damage should be immediately reported to the
carrier.
• When the system is received (or shortly thereafter) an Uster
Technologies, Inc. technician will arrive to install it. Do not
attempt to set up the system by yourself. Refer to the Appendix,
HVI 900 System Installation Guide/Report, during the installation
procedure. This report, along with a copy of the Status Listing,
should be returned to Uster Technologies, Inc., Knoxville, once
installation has been completed.
Attention: If the system is to be stored before being
used, inside storage
is
required
in a location that is
protected from excess moisture, corrosive atmospheres,
and chance of physical damage. Conditioned storage is
recommended, but is not required. If the instrument
has been exposed to a cold environment, condensation
may form on cold surfaces when the instrument is
moved into a warm area. In such situations, allow the
instrument to warm and dry thoroughly before
proceeding with installation.
The following procedures are to be performed for each cabinet with the
assistance of Uster Technologies’ personnel or an authorized Uster
Technologies, Inc. agent. Detailed installation procedures for
connecting the cables and setting up the system are provided to
authorized personnel in the Service Manual.