The HVI 900 System has been designed to reduce maintenance to a
minimum. However, to keep the instruments in top condition, a few tasks
must be performed routinely.
3 Cleaning the System
Maintenance can be divided into four categories:
As required
After each shift
Daily
Weekly
3.4 As Required
Excess cotton should be removed from the Fibrosampler 192-1 carding
plate as required. Refer to the chapter titled “Fibrosampler 192" for
details on cleaning and maintaining the Fibrosampler.
3.5 After Each Shift
After each shift, the excess fiber that has gathered in the instrument
during the measurement procedures should be removed using a vacuum
cleaner.
Swing the monitor arm away from the Length/Strength cabinet so

Table of Contents