3. Installation process
3. INSTALLATION PROC ESS
About the installation process
The installation of the complete system is s plit up in tw o parts, installation of the projector and the installation of the cooler unit as
top pack or stand alone pack .
Overview
Installation process pro jector
Installation process top cooler
Installation pr ocess stand alone cooler
Software upgrade
Startingupandadjustingthesystem
3.1 Installation process projector
Installation process from A to Z
1. Check if all installation requirements are fullled such as the env ironment conditions of the installation are a, electrical facili-
ties, etc. N ote that a solid pedestal is required to support the projector. For more info s ee topic installation requirements.
2. P h ysical installation of the projector upon its pedestal.
3. E lectrical connection with the power n et. Depending the projector type, see chap ter "Connecting the DP xK-17/23BLP with
the power net", page 31 or chapter "Connecting the DPxK -36BLP with the power net", page 32.
4. In stallation of the lens. First select a lens with appropriate throw ratio covering the screen size and the projector - screen
distance. Then install the lens in the lens holder of the projector. For more information about available lenses, lens selection and
lens installation see chapter "Lenses & lens holder", page 63.
Caution: The projector is deliver ed with a plastic cover inside the Lens Holder. R em ove the cover prior to installing the lens.
5. In stallation of the ICMP, IMB, IMS or HDSDI input module. (only in case no ICMP, or IMB or IMS or HDSDI is factory installed).
6. Installation of the HDDs. In case the HDDs of the ICMP are delivered separat
ed from the projector rem ove the protection tape
from the HDD input slots and install all three HDDs as described in the proc edure "Installing a HDD into the ICMP", pag e 111.
Make sure that all HDD s in the ICMP H DD set h ave the s ame storage c apacity. See label on top of the HDD to know the s torage
capacity.
7. Installation of the Cooler. In case of a top pack installation, see "Installation process top cooler", page 2 3. In case of a stand
alone combination, see "Installation process stand alone cooler", page 24.
8. ( O ption) Installation of the optional C ommunicator touch panel on the projector. In both stand alone and top pack solutions, it
is possible to install a Barco commu nicator touch panel. Note: If the customer chose the top pack solution it is recommended to
install the top cooler rst, then the touch pan el.
9. Upgrade all software to the latest av ailable version. See "Software upgrade", page 24.
10.Start up your projector and adjust the system. See "Starting up and adjusting the system", page 24.
3.2 Installation process top cooler
Installation process from A to Z
1. A ssem bling of the cooling box housing. The housing is delivered as a at pack and should be pre-assembled during the
installation process.
2. Moun ti ng of the cool e r hou sing on its sup port (frame).
3. M ounting of the Front support on the cooler frame.
4. M o unting the empty cooler assem bly on the projec tor.
5. In sert the cooler units and lters.
6. E stablish the hose connections (4x) between the c ooler and the projector. Connect also the four cab les.
7. If desired, mount the Communicator touch panel on the support foot of the cooler support and make the connections with the
projector.
R5906753 DPXK BLP SERIES 20/11/2017
23