Crane operation
11.4 Operation of the rated capacity limiter
Operating manual 3 302 709 en 11 - 39
GMK5150L
12.01.2018
The confirmed boom system (1) or (2) is
displayed.
Reeving
• (A) – Select and confirm the display for the
hoist to be used for lifting the load, for
example, display (1) for the main hoist –
symbol (3) is orange.
• (B) – Select the currently rigged reeving (2),
e.g. 8-fall.
• Confirm the selection and leave the
display (1) – symbol (3) grey.
s