Status Indicator Raps
123-397 UI Manager RAP
The UI software failed.
Initial Actions
Power Off/On
Procedure
Disconnect and reconnect the electrical connections on the UI PWB (PL 11.2) and P/J388 on
the ESS PWB (PL 9.2)
If the problem persists reload Software (ADJ 9.3.1).
If the problem persists replace the UI PWB (PL 11.2).
If the problem persists replace the ESS PWB (PL 9.2).
123-398 Release Queue RAP
The UI software failed a full queue release.
Initial Actions
Power Off/On
Procedure
Disconnect and reconnect the electrical connections on the UI PWB (PL 11.2) and P/J388 on
the ESS PWB (PL 9.2)
If the problem persists reload Software (ADJ 9.3.1).
If the problem persists replace the UI PWB (PL 11.2).
If the problem persists replace the ESS PWB (PL 9.2).